The brochure shows both gabled roof arrangements and terrace extensions, including projects labelled 318 m² and 110 m². Select the roof layout around the building connection and water routes, not the total case area.

Compare roof direction and interfaces
A wall-linked slope and a gabled arrangement create different high points and gutter lines. Ask for elevations showing where modules meet and how fabric movement is coordinated at those interfaces.
Plan around the occupied terrace
For a bar extension, locate entrances, serving counters and seating first. Coordinate posts and lowered roof edges with the circulation plan before using a case photograph to choose the visual treatment.
Keep case areas and model limits separate
Neither the 318 m² nor the 110 m² project label establishes a single-unit limit or the exact installed submodel. Request a module schedule and model-specific specification for a comparable project.
Choose the ridge and drainage together
A two-slope arrangement changes where the roof is highest and where water is collected. Show the centre line, both lower edges and any connection to the existing building in section. The bar counter, tables and service route should be included below it. Do not select a gable shape only for its appearance; the joints and outlets need to work with the actual site, particularly where a new roof meets an existing canopy.
Check what remains when the fabric is open
The frame and ridge arrangement remain visible when fabric retracts. Ask which direction each section travels and whether one side can operate independently. Review the open view from the bar as well as from the tables. Lighting and signs should be positioned around the moving roof, not added later where they could obstruct folding fabric or access to its guides.
Resolve the ridge and both eaves
A gable arrangement needs coordinated geometry on both slopes. Show the ridge position, the two front clearances and how the roof meets any adjacent building. Check the operating and drainage arrangement on each side rather than assuming symmetry resolves every detail. Compare the view with both roof sections open and with only one operating. For a bar terrace, relate the ridge and supports to the counter, circulation and lighting positions.
Coordinate the roof with the supporting structure
A product outline is only one part of the installation. Show how the roof loads will pass into the wall, posts or supporting frame, and agree who will check the existing structure. The final arrangement should also show how water leaves the roof and where cables enter without obstructing a moving component. If supports or drainage change, update the roof drawing as well as the site plan. Keep fabrication dimensions separate from preliminary measurements until the interfaces have been agreed; otherwise a correctly manufactured product can still arrive with an unsuitable connection to the building.
Specifications behind this guide
T-series retractable folding roofs
- Projection up to 7 m
- T700
- Projection up to 9 m
- T900
- Projection up to 12 m; area ≤72 m²
- T1200
| Model | Width limit (m) | Projection limit (m) | Rail section |
|---|---|---|---|
| T700 | 8 | 7 | 130 × 70 × 2.5 mm |
| T900 | 8 | 9 | 170 × 98 × 2.5 mm |
| T1200 | 8 | 12 | 200 × 130 × 2.5 mm |
T1200: width ≤8 m, projection ≤12 m and total unit area ≤72 m² must all be met. Standard PVC fabric; Sauleda available as an option.
See model detailsBefore you approve the order
- Confirm model, overall width, projection and the drawing revision in one written order.
- Match mounting parts, fabric reference, finish and controls to the quotation; document any substitution.
- Agree delivery contents, site-work responsibilities, operating instructions and the service contact.